This week in Burwell’s Bluff:

We were very fortunate to receive some great weather this week and the construction process moved along very nicely.

  • Lot 10- Finishing touches are being made, we are entering the final inspection process, and the landscaping process will begin this week.
  • Lot 11- The driveway and Sidewalks have been installed, the interior painting process will continue into this week.
  • Lot 15- The foundation is being installed.
  • Lot 22- The footings are installed, and the foundation process will begin this week.

We are extremely excited about the Open House in the Osprey on Lot 10 during the Kingsmill Championship, so please continue to spread the news and come and see us!