Posted by Kingsmill Realty on Sunday, June 10th, 2018 at 7:42pm

I hope everyone is enjoying the tremendous weather this weekend! Summer is officially here and Kingsmill is absolutely a great place to be. I am excited to announce that Lot 10 is officially under contract, and is set to close later this month. We are excited about the opportunity to continue to invest in this neighborhood, and without those who want to be apart of Burwell’s Bluff, this wouldn’t be possible. Have a great week!

Construction update:

  • Lot 10: Under Contract.
  • Lot 11: The flooring is being installed, and the landscaping process will begin this week.
  • Lot 15: We are in the middle of the framing phase and this will continue in the following weeks.
  • Lot 16: We are in the permitting phase.
  • Lot 22: We are in the middle of the framing phase and this will continue in the following weeks.
  • Lot 23: Final plans are in progress.
  • Lot 25: We are in the permitting phase.