This week in Burwell’s Bluff:
I hope everyone had an excellent holiday weekend! Things are continuing to progress nicely, with 2 homes being finished in the next few months while 2 more homes are in the early stages of construction. A friendly reminder that the Osprey on Lot 10 is still on the market, so call our Real Estate office today for further information!
- Lot 10: The interior finishes installation is almost complete, hardwood floors have been installed, the appliances have been installed. The next few weeks will consist of finishing up the home and putting on some finishing touches.
- Lot 11: Kitchen cabinets have been installed, ceramic tile is in progress, and the interior painting process is still taking place
- Lot 15: The footing installation is underway.
- Lot 22: Footing installation will begin next week.
It is hard to believe that the Kingsmill Championship is now under 40 days away. The weather is changing and spring is officially upon us! Stay tuned for further updates, and have a great week!
Leave A Comment