Real Estate Blog

This week in Burwell’s Bluff:

We were very fortunate to receive some great weather this week and the construction process moved along very nicely.

  • Lot 10- Finishing touches are being made, we are entering the final inspection process, and the landscaping process will begin this week.
  • Lot 11- The driveway and Sidewalks have been installed, the interior painting process will continue into this week.
  • Lot 15- The foundation is being installed.
  • Lot 22- The footings are installed, and the foundation process will begin this week.

We are extremely excited about the Open House in the Osprey on Lot 10 during the Kingsmill Championship, so please continue to spread the news and come and see us!

Have a great week.

 

IMG_3324

883 Views, 0 Comments
Read Full Post

This week in Burwell’s Bluff:

Things are moving along nicely as we now have 4 homes under construction in Burwell’s Bluff. We are excited to announce that during the Kingsmill Championship we will be having an open house in the Osprey on Lot 10, so please come by and see us.

  • Lot 10:The finish grading has begun and the hardwood floors are installed.
  • Lot 10:We are in the process of obtaining the final inspection, and the landscaping will begin this week.
  • Lot 11: The ceramic tile is complete, and interior painting is still in progress.
  • Lot 11: The driveway will be installed this week.

Lots 15 and 22 are well underway as Lots 10 and 11 finish up here in the following weeks. As the Kingsmill Championship plans begin to take shape,

870 Views, 0 Comments
Read Full Post

This week in Burwell’s Bluff:

I hope everyone had an excellent holiday weekend! Things are continuing to progress nicely, with 2 homes being finished in the next few months while 2 more homes are in the early stages of construction. A friendly reminder that the Osprey on Lot 10 is still on the market, so call our Real Estate office today for further information!

  • Lot 10: The interior finishes installation is almost complete, hardwood floors have been installed, the appliances have been installed. The next few weeks will consist of finishing up the home and putting on some finishing touches.
  • Lot 11: Kitchen cabinets have been installed, ceramic tile is in progress, and the interior painting process is still taking place
  • Lot 15: The footing
873 Views, 0 Comments
Read Full Post

This week in Burwell’s Bluff:

The Kingsmill Championship scoreboard is up, and Burwell’s Bluff has some of the best views of the River Course that the entire neighborhood has to offer. The construction permitting signs have been delivered for lots 15 and 22, and those signs will soon be installed. We are excited to break ground this week on these two lots as well! Both lots 10 and 11 are nearing completion and will be completed in the next 2 months.

Lot 10: Fixtures are installed, as well as the hardwood floors on the first floor. Exterior deck and porch railings have also been installed.

Lot 11: Interior painting has begun, as well as cabinet installation. Driveway is being prepped for pouring.

Thank you for sharing this update with others.

907 Views, 0 Comments
Read Full Post

This week in Burwell’s Bluff:

It has been another very productive week this week down at Burwell’s Bluff. We are certainly excited to announce that we officially have building permits for lots 15 and 22; the footing process will begin in the next few weeks.

Lot 10:

  • Fixtures are in the completion phase, hardwood floor installation will begin next week.
  • Exterior deck and porch railings installation will be installed this week.

Lot 11:

  • Cabinets have been delivered and will soon be installed.
  • Interior trim is complete, interior painting will begin next week.

 As the construction process continues in Burwell’s Bluff, we want to take a moment to thank you for all the support and feedback thus far. We realize that it is not

840 Views, 0 Comments
Read Full Post

This week in Burwell’s Bluff:

Things are moving along nicely in Burwell’s Bluff as the homes on lots 10 and 11 near completion in the next few months. It will be nice to have the homes finished right around the time of the Kingsmill Championship. We will keep you updated on any tents or marketing stations that we might set up during the tournament. 

The Heron and Osprey this week:

  • The garage doors have been installed on Lot 10, and the plumbing and lighting fixtures will be installed this week. The heating and air equipment will be installed as well.
  • The subcontractors will be working on the deck area this week, and the interior doors have also been delivered for the Heron on lot 11. Both the interior doors and interior trim will be
883 Views, 0 Comments
Read Full Post